Lusaka has embarked on a major 5-year sanitation improvement programme, the Lusaka Sanitation Programme, funded by EIB, KfW, AfDB, WB and the Government of Zambia, with a total investment of 240 MEUR in new wastewater treatment plants,
520 km of sewers, decentralised wastewater treatment systems, 100 public toilets, some 12,000 on-site sanitation units and faecal sludge management.
The project implementation is being managed and monitored by a Project Management Unit within the Lusaka Water and Sewerage Company, supported and assisted by a Project Implementation Consultant, PIC.
LOCATION:
Lusaka, Zambia, Africa
PERIOD:
2016-2021
CLIENT:
European Investment Bank, EIB
Beneficiary:
Lusaka Water and Sewerage Company, LWSC
Consortium:
COWI A/S (lead partner), PM Group and Artelia. COWI Zambia (sub-consultant)
COWI'S SERVICES:
Karsten Vesth-Hansen
Project and Market Director
Water, Denmark
Tel:
+45 56402268